04REV_Utica Street & Utility Improvements Project Update 20260707

Week of July 6:

  • The Contractor has indicated that they intend to start with the sanitary sewer cleaning & televising on Wednesday, July 8th. This work is being done as a precursor to installing the liner which will happen in the future.
    • There will be no interruption to sewer service during the sanitary sewer cleaning and televising process.

Project Notes:

  • A sewer lining information sheet and example door hanger work notice were uploaded to the city’s website. We encourage all residents to check out both.

Contact

Please reach out to Nolan Boice, the Resident Project Representative, at 507-884-4877 or nolan [email protected] with any questions.

Note – The reported schedule will always be flexible due to weather and other reasons. This update is meant to provide information as we know it at the time of the update preparation. Real time schedule updates can be obtained by calling Nolan Boice