Skip to content

Beginning at 6:30am on October 1st: All traffic wishing to access Schultz Street & Railroad Street must enter/exit from Center Street / Co Road 33.

Welcome to the City of Utica, MN!

City of Utica logo - City of Utica
  • Home
  • City Government
    • City Council
    • Agendas & Minutes
    • Ordinances
    • Elections
    • Calendar
  • Residents
    • Licenses & Permits
    • Emergency Services
    • Water & Sewer Utilities
  • News
  • About
  • Contact

News & Updates

News & UpdatesVision Design
  • 2026 STREET AND UTILITY IMPROVEMENTS PROJECT UPDATE #21 (Contract 3)

    21_Utica Street & Utility Improvements Project Update 20261023

    Week of October 19:

    · The contractor made the final connection to the existing watermain system, completing the utility work in Phase 2 along E Main Street.

    · All […]

  • 2026 STREET AND UTILITY IMPROVEMENTS PROJECT UPDATE #20 (Contract 3

    20_Utica Street & Utility Improvements Project Update 20261016 (1)

    Week of October 12:

    · The contractor finished sewer service, and water service installations in Phase 2C along East Main Street.

    · The contractor continued to […]

  • 2026 STREET AND UTILITY IMPROVEMENTS PROJECT UPDATE #19 (Contract 3)

    Week of October 5:

    · The contractor continued sewer service, watermain, and water service installations in Phase 2C along East Main Street.

    · The contractor also worked on road construction in Phase 2A along East […]

  • 2026 STREET AND UTILITY IMPROVEMENTS PROJECT UPDATE #18 (Contract 3)

    Week of September 28:

    • The contractor completed watermain and water service installations in Phase 2A along East Main Street.
    • The contractor has also completed a segment of road construction in Phase 2A along East Main […]
  • 2026 STREET AND UTILITY IMPROVEMENTS PROJECT UPDATE #17 (Contract 3

    17_Utica Street & Utility Improvements Project Update 20260930

    Week of September 28:

    • The contractor has completed watermain and water service installations in Phase 2A along East Main Street.
    • The contractor has also completed sections of […]
  • 2026 STREET AND UTILITY IMPROVEMENTS PROJECT UPDATE #16 (Contract 3)

    16_Utica Street & Utility Improvements Project Update 20260925

    Week of September 21:

    · The contractor continued watermain and water service installations in Phase 2A along East Main Street.

    · The contractor also began road construction […]

12345Next

200 S Center St SE
PO Box 431
Utica, MN 55979

(507) 932-5293

This number is for inbound voicemails only

[email protected]  ♦General Inquiry

[email protected] ♦Agendas/Minutes ♦Building Permits ♦Elections ♦Utica School Rental

© 2026 City of Utica. All Rights Reserved.

  • Privacy Policy
  • Accessibility Statement
  • Vision Design Group, Inc.
  • Privacy Policy
  • Accessibility Statement
  • Vision Design Group, Inc.
Page load link