Utica Street & Utility Improvements Project Update 20260702
Week of June 29:
- The scheduled sanitary sewer cleaning & televising was postponed.
Week of July 6:
- There is no planned or scheduled work this week.
Week of July 13:
- The Contractor has indicated that they intend to start with the sanitary sewer cleaning & televising on or around July 13th. This work is being done as a precursor to installing the liner which will happen in the future.
- There will be no interruption to sewer service during the sanitary sewer cleaning and televising process.
- The Contractor has also indicated that they intend to start the watermain installation in Phase 1A (along the driveway of Whitewater Milling) on or around July 13th.
- No road closures are scheduled for this work.
Project Notes:
- Thank you in advance for your continued attention to project safety in the work zone.
- A sewer lining information sheet and example door hanger work notice were uploaded to the city’s website. We encourage all residents to check out both.
Contact
Please reach out to Nolan Boice, the Resident Project Representative, at 507-884-4877 or nolan [email protected] with any questions.
Note – The reported schedule will always be flexible due to weather and other reasons. This update is meant to provide information as we know it at the time of the update preparation. Real time schedule updates can be obtained by calling Nolan Boice.