Week of August 17:

  • The contractor has indicated that the reclaimer will be in town on August 18th to reclaim the blacktop along E Main Street. Partial road closures are planned for this work.

Week of August 24:

  •  The contractor has indicated that they plan to start sanitary sewer service replacements along E Main Street. Road closures for segments of E Main Street are planned for this work.

Project Notes:

  • Thank you in advance for your continued attention to project safety in the work zone.
  • A sewer lining information sheet and example door hanger work notice were uploaded to the city’s website. We encourage all residents to check out both.
  • A phasing plan figure has been added to the city website. This is for residents to reference and understand where work is occurring when phases are called out in the weekly updates. We encourage all residents to check it out.

Contact:

Please reach out to Nolan Boice, the Resident Project Representative, at 507-884-4877 or nolan [email protected] with any questions.

Note – The reported schedule will always be flexible due to weather and other reasons. This update is meant to provide information as we know it at the time of the update preparation. Real time schedule updates can be obtained by calling Nolan Boice.