08_Utica Street & Utility Improvements Project Update 20260731

Week of August 3:

· The sewer lining subcontractor has indicated that they will begin installation of CIPP liners throughout the entire project the week of August 3rd.

· With liner installation, there will be temporary restrictions on your water & sewer service usage. Service restrictions typically last around 4 hours and can occur anytime from 7am – 5pm. Residents will be notified of the date, time, and duration of all service restrictions 48 hours prior to liner installation via door hanger from the lining contractor.

· A sewer lining information sheet and example door hanger work notice were uploaded to the city’s website. We encourage all residents to check out both.

Week of August 10:

· There is no planned or scheduled work this week.

Project Notes:

· Thank you in advance for your continued attention to project safety in the work zone.

· A sewer lining information sheet and example door hanger work notice were uploaded to the city’s website. We encourage all residents to check out both.

· A phasing plan figure has been added to the city website. This is for residents to reference and understand where work is occurring when phases are called out in the weekly updates. We encourage all residents to check it out.

Contact:

Please reach out to Nolan Boice, the Resident Project Representative, at 507-884-4877 or nolan [email protected] with any questions.

Note – The reported schedule will always be flexible due to weather and other reasons. This update is meant to provide information as we know it at the time of the update preparation. Real time schedule updates can be obtained by calling Nolan Boice.