03_Utica Street & Utility Improvements Project Update 20260626
2026 STREET AND UTILITY IMPROVEMENTS PROJECT UPDATE #3 (Contract 3)
Week of June 22:
- The Contractor cut down the trees designated for removal.
Week of June 29:
- The Contractor has indicated that they intend to start with the sanitary sewer cleaning & televising on or around June 29th. This work is being done as a precursor to installing the liner which will happen in the future.
- There will be no interruption to sewer service during the sanitary sewer cleaning and televising process.
Project Notes:
- Thank you in advance for your continued attention to project safety in the work zone.
- A sewer lining information sheet and example door hanger work notice will be uploaded to the city’s website soon. We encourage all residents to check out both.
Contact
Please reach out to Nolan Boice, the Resident Project Representative, at 507-884-4877 or nolan [email protected] with any questions.
Note – The reported schedule will always be flexible due to weather and other reasons. This update is meant to provide information as we know it at the time of the update preparation. Real time schedule updates can be obtained by calling Nolan Boice.